Activity-in-Diagram: Formulate Test Strategy

CreatorTim Ramey

Description

The CyWG plans a series of Phase 3 and/or Phase 4 activities beginning with contractor (prototype or development) test, potentially as early as sub-component and sub-component integration events, to evaluate the areas of concern identified in the previous tasks and inform the acquisition program decision s as identified in the DEF.

Owning Diagram A24: Prepare for Phase 3 and Phase 4 Cybersecurity DT&E Events

Input

identified risks

cyber security scenarios

Output

TEMP updates

cybersecurity T&E strategy update

Control

cybersecurity T&E strategy

Cheif Developmental Tester

Test and Evaulation Master Plan (TEMP)

Mechanism

Lead DT&E Organization